Securing a nuclear site

Home 5 References 5 Securing a nuclear site

 Project features

  • TOTAL POWER: 2×50 kVA — 2 substations
  • TRANSPORT VOLTAGE: 3,200 V single phase
  • NETWORK LENGTH: 2,500 meters
  • LOCATION: France
  • YEAR: 2021 & 2026

PROJECT OBJECTIVES

The security fence lighting system uses light points distributed over 2,500 meters, each equipped with two LED lamps.
For confidentiality reasons, no names or actual photos will be included in this document.

CUSTOMER NEEDS

Create a redundant dual power supply to maximize the safety of the lighting installed along the fence. The power supply must be functional under all circumstances.

CUSTOMER NAME 

INEO

OUR SOLUTIONS IMPLEMENTED

Installation of two step-up substations powered by two different low-voltage sources. Each step-up substation feeds a 3,200V mains supply consisting of watertight transformers installed in a pit. The dual 3,200V and low-voltage networks provide the best guarantee of power supply.

MATERIAL USED

  • 57 watertight transformers IP68, MODULO 2 kVA 3,200 V / 230 V,
  • 2 step-up transformer substations 50 kVA 400 V / 3,200 V with one 3,200 V feeder

CUSTOMER BENEFITS

SECURE THE INSTALLATION, BURIED SOLUTION

POWER SUPPLY REDUNDANCY

COMPACT STEP-UP SUBSTATIONS