Installation of two step-up substations powered by two different low-voltage sources. Each step-up substation supplies watertight transformers installed in a pit from two on load switch.

Securing a military site
read more
Installation of two step-up substations powered by two different low-voltage sources. Each step-up substation supplies watertight transformers installed in a pit from two on load switch.
Creation of several three-phase 5500 V networks equipped with watertight transformers installed in pits, transformers powered by 3×16 mm² cables.
Project features TOTAL POWER: 630 kVA TRANSPORT VOLTAGE: 5500 V NETWORK DISTANCE: 16 KM LOCATION: Fujairah, UAE YEAR: 2008 PROJECT OBJECTIVES Providing the electrical power supply for the lighting of the security perimeter walls at Fujairah Airport, UAE. Total length:...