Reduce costs and enable the power supply of road equipment spread over 25 km from three energy sources. Powering different sections ranging from 3 to 11 kilometers in length.

Reduce costs and enable the power supply of road equipment spread over 25 km from three energy sources. Powering different sections ranging from 3 to 11 kilometers in length.
PROJECT FEATURES TOTAL POWER: 1880 kVA TRANSPORT VOLTAGE:5500 V / 950 V NETWORK LENGTH: 30 km LOCATION: Reunion Island - France YEAR: 2008 PROJECT OBJECTIVES Power supply for road equipment, traffic management, variable message signs, cameras, structures (viaduct a...
Project feautures TOTAL POWER: 50 kVA TRANSPORT VOLTAGE: 950 V NETWORK DISTANCE: 1.3 KM LOCATION: Borgo, Corse YEAR: 2012 PROJECT OBJECTIVES Supplying power to the ring road lighting. CUSTOMER NEEDS Energy source (400V) available from beginning of installation....
Project feautures TOTAL POWER: 6000 kVA TRANSPORT VOLTAGE: 6600 V NETWORK DISTANCE: 74 KM LOCATION: Mafraq, UAE YEAR: 2010 PROJECT OBJECTIVES Powering highway lighting, 90 km long with more than 1500 poles each of 2000W. CUSTOMER NEEDS Cope with inadequate energy...
Project feautures TOTAL POWER: 50 kVA TRANSPORT VOLTAGE: 950 V NETWORK DISTANCE: 0.65 KM LOCATION: A6, France YEAR: 2008 PROJECT OBJECTIVES Supply the sanitaries, the lighting, the signalings. CUSTOMER NEEDS To carry 50 kVA on 650 meters to supply the uses of a...